Havering has awarded a £9.71m contract to replace the cladding, windows and roof at Highfield Towers, Collier Row. Work is due to start in January 2027.

Havering Council has approved a £9.71 million contract to replace the cladding, windows and roof at Highfield Towers, the council tower block on Hillrise Road in Collier Row.

The contractor, Lawtech Group, is due on site in January 2027. The council expects the building work to continue until autumn 2028.

The decision was made on 12 November. It takes effect on 19 November unless councillors call it in by 18 November.

Overview

  • Contract: £9.71m including a 10% contingency, a direct award to Lawtech Group
  • The work: new insulated cladding, new windows throughout, new smoke vents on the landings and a new roof covering
  • Government help: about £6m from the Cladding Safety Scheme, for the cladding only
  • Leaseholders: 13 face an estimated £19,862.68 each for the windows and roof; they cannot be charged for the cladding
  • Timetable: on site January 2027, finishing autumn 2028

What is being replaced

The decision report lists the work in the contract:

  • the rainscreen cladding, replaced with new insulated cladding that can carry ducts for gas risers and a future communal heating system
  • every window in the block
  • the automatic opening smoke vents on the landings
  • the roof covering

Lawtech already knows the building. It removed the high-pressure laminate cladding from the back of the block and put up temporary cover between June and August 2025. The report says that was done “at short notice on the advice of a fire engineer”.

Why the inside work has been split off

Cabinet approved the project in April 2025 at an indicative £7.5 million. That figure covered more than this contract: it also included sprinklers and new fire alarms inside the flats.

The report says Lawtech, as a cladding specialist, “proved less able” to plan the work inside people’s homes. So that work has been taken out of its contract:

  • Fire alarms and fire-stopping: another firm, AJS Ltd, is already replacing alarms and checking flats under an existing council contract, according to the council’s Highfield Towers page.
  • Sprinklers: these need a separate Cabinet decision. The council’s page says they are “unlikely to commence until spring 2029 at the earliest”.
  • Lifts: the council is looking at a separate lift firm working inside while the cladding goes on outside. We reported on 10 November on the plan for a firefighting lift at Highfield Towers.

Who pays

The report puts the full cost of the outside work, including consultants, at £10.344m. It expects to pay for it like this:

Source Amount
Government Cladding Safety Scheme grant £6.000m
Council housing account borrowing £4.086m
Leaseholders £0.258m

The grant covers the cladding only, not the windows or the roof. The report says the scheme has confirmed the approximate figure, but the exact sum still has to be finalised.

What it means for leaseholders

There are 13 leaseholders in the block, 17% of the flats. Under the Building Safety Act 2022, the council cannot pass on the cost of the cladding or the smoke vents.

They do have to contribute to the windows and roof, which the report says have reached the end of their life. Its estimate per flat is:

Item Cost per flat
Windows £15,437.17
Roof £3,386.47
Contingency £460.53
Admin at 3% £578.53
Total £19,862.68

Leaseholders are charged after the work is finished and the costs are reviewed. The formal consultation they are owed under Section 20 of the Landlord and Tenant Act 1985 is due to finish on 20 November, and the contract award depends on it.

What it means for tenants

  • Start date: the council says the contractor should be on site in January 2027, if the Building Safety Regulator approves the design. It expected that approval by 13 November.
  • Disruption: the work runs until autumn 2028. The council plans to redecorate the communal areas once all the building safety work is finished.
  • Questions: the council says it will hold more drop-in sessions and a “meet the contractor” event. Progress posters go up in the lift lobby.

Sources