Both lifts will stop on every floor at Highfield Towers and three Hornchurch tower blocks. The cost has risen by £942,276, and leaseholders will not be charged.

Residents of Highfield Towers in Collier Row and three council tower blocks in Hornchurch will get a lift that firefighters can use. Both lifts in each block will also stop at every floor, instead of one serving odd floors and the other even ones.

Havering Council has added £942,276 to the cost of the work. Leaseholders in the four blocks will not be charged for it. The decision was signed on 29 October and took effect on 5 November (decision record).

Which blocks

The four blocks are:

  • Highfield Towers, Hillrise Road, Romford RM5 3DL
  • Overstrand House, Sunrise Avenue, Hornchurch RM12 4YW
  • Parkview House, Sunrise Avenue, Hornchurch RM12 4YW
  • Uphavering House, Park Hill Close, Hornchurch RM12 4YX

The three Hornchurch blocks make up the Petra estate. The addresses are from the council’s high-rise building safety pages.

What the work involves

The decision report says the work follows the Building Safety Act, which came into force on 1 October 2023. In each block:

  • one lift will be upgraded to a firefighting lift, to the British Standard BS 8899:2016
  • that lift will get a second, backup power supply
  • both lifts will stop on every floor, which the council says gives residents “much better accessibility” and gives London Fire Brigade access

Highfield Towers was refurbished about eight years ago and the Petra blocks about three years ago. Neither project included firefighting lifts. The council says the aim is “equal levels of building safety in all of our blocks”.

Why the cost went up

The council first added the four blocks to its lift contract in January 2026, at £676,000. More detailed surveys, and questions from the Building Safety Regulator, then widened the job. Delays in getting the regulator’s approval to start added time and cost.

Bar chart of the extra £942,276 added to Havering's tower block lift contract: Highfield Towers firefighting lift £361,220, Petra estate backup power £178,056, machinery storage £175,000, contingency £100,000, inflation uplift £90,000, consultants £20,000, second power cables for six blocks £18,000.
Chart by Romford Today
Share this chartFacebookWhatsAppX

The extra £942,276 breaks down as:

Item Cost
Highfield Towers firefighting lift £361,220
Petra estate backup power for firefighting £178,056
Storing lift machinery, 2025/26 and 2026/27 £175,000
Contingency for regulator delays £100,000
Inflation on labour since October 2024 £90,000
Lift and design consultants £20,000
Second power cable to six other blocks £18,000

The work is going to Lift Specialists Ltd, which already holds the contract for six other tower blocks. Those are Kipling and Dryden Towers in Harold Hill and four blocks on the Delta estate in Gidea Park. The contract is extended by seven months. The total project cost, including consultants, is now £5,472,754, up from an original £3,854,478.

The council rejected a fresh tender. It says that would take nine months, and a new contractor could add six more by re-doing the designs.

Who pays

The council will not recharge leaseholders. The report gives three reasons:

  • it has not charged leaseholders for similar fire safety work before
  • consulting leaseholders on charges would delay the work
  • future maintenance and replacement of the new equipment would be chargeable

The finance section notes the trade-off. Without leaseholder contributions, the cost falls on the Housing Revenue Account, the budget paid for by council tenants’ rents. The 2026/27 budget for resident safety works is £10.303 million. At the end of July, £4.213 million of it was forecast to slip into later years, so the council says there is room this year.

What it means for you

  • If you live at Highfield Towers, the lift work may run alongside the new cladding. The council’s Highfield Towers page expects the Building Safety Regulator’s approval by 13 November, a contractor on site in January 2027, and building work until autumn 2028. It says it is looking at a separate lift contractor so the lifts are done at the same time.
  • Leaseholders in all four blocks will not get a bill for this work. Future maintenance of the new lifts can be recharged.
  • No start date for the lift work is given in the report. The council’s pages say it will keep residents informed block by block.

Sources