Havering has awarded a £2.65m contract to re-roof the leaking Town Hall in Romford. Work starts in early 2027 and the Council Chamber will close for 12 weeks.

Havering Council has approved a £2.65 million contract to replace the roof of the Town Hall on Main Road, Romford. Water gets in so often that it is damaging the roof and the ceilings below.

The work is due to start in early 2027 and last 24 weeks. The Council Chamber, where full council meets, will be out of use for the first 12 weeks.

The decision was made on 12 November by the council’s Director of Place. It takes effect on 19 November unless councillors call it in by 18 November.

Overview

  • Contract: £2,648,953.14 to Beardwell Ltd, from the existing capital budget
  • Why: a condition survey found water ingress, failed weatherings and worn parapet copings across the roof
  • When: early 2027, for 24 weeks
  • Council Chamber: closed for about 12 weeks at the start of the work
  • Solar panels: expected to save about £11,000 a year on electricity

Why the roof needs replacing

The Town Hall is a Grade II listed building and the council’s headquarters. The decision report says a survey found “widespread deterioration” of the roof coverings.

It says water ingress and leaks “are a regular occurrence and are leading to further deterioration of the roof and ceilings”.

The council rejected doing nothing and rejected waiting another year. Both, the report says, would push up the cost and risk emergency repairs.

What the contract covers

Cabinet approved the original scheme in September 2024: a new flat roof and roof lanterns, repairs to the parapet walls, solar panels and new heating and cooling units. Listed building consent has been granted.

The design has grown since then. The report lists these additions:

  • an extra lower flat roof area
  • full replacement of the pipework on the roof
  • a steel frame to carry the weight of the solar panels
  • air conditioning on the first floor of the West Wing
  • demolition of the corridors that linked to a modular building that has already gone
  • new surfacing, a ramp and fencing in the rear courtyard
  • new lighting in the Council Chamber
  • redecoration only where the work disturbs it

What it costs

The price has risen from the estimate given in September 2024. The report blames tender price inflation, supply chain problems and the wars in Ukraine and the Middle East, as well as the extra work.

It does not publish the earlier estimate. It says the new price is within the budget already set aside, so no extra money is needed. The fees of the two consultants on the project, STACE and Purcell Architects, are also going up.

Seven firms were invited to bid through the London Housing Consortium framework. Two did. Bids were scored 60% on price and 40% on quality, and Beardwell Ltd came out on top.

The report was signed off by officers on 15 October. It warned that Beardwell had agreed to hold its price only while the decision was made “until the end of October”, after which the price “may be reconsidered and increased”. The decision was signed on 12 November. The published papers do not say whether the price was extended.

What it means for you

  • Council meetings: the Council Chamber will be shut for about 12 weeks from early 2027. The report does not say where meetings will move to.
  • Visiting the Town Hall: apart from the chamber and parts of the West Wing’s first floor, the council does not expect other areas to close. The first-floor corridor by the committee rooms will stay open under protective scaffolding.
  • The cost: the report says the work is paid for from money already in the council’s capital programme for corporate buildings, with no extra funding needed.